LESCO New Connection 2025

LESCO Meter Connection Type

There are two categories for the LESCO new meter connection type:

Load Type

  • Load Up to 15 KW
  • Load over to 15 KW
  • Load up to 70 KW
  • Increase up to 500KW

All Load 66 KV and Higher from this

Connection Type

Choose the connection type from the following name list: 

  • Local
  • Agriculture
  • Overall services
  • Commercial/Business
  • Business Organizations
  • Tubewell
  • Manufacturing
  • Temporary
  • Street Light
  • Business Company

You have options to applying for the industrial, commercial and corporate company connections, then you must provide the NTN and STRN, because this is necessary requirements for applying.

Procedure for LESCO New Connection by Hand

  • Print or collect Application Form: Download or print the new connection application form, from their website or collect it from your nearest LESCO office.
  • Fill Out the Form: Carefully read the form and fill your details on it. Attach all required documents as mentioned in it and complete all paperwork.
  • Submit the Application: Submit the form with all documents to your nearest local LESCO office. There processing time take up to 15 days to complete.
  • Receive Demand Notice: Once the application is proceeded, they will give you the demand notice. Then, Pay the connection charges and submit it.
  • New Connection installation: After completing process, your new connection will be installed in a couple of days.

Procedure to Apply LESCO New Connection through online portal |complete guide

There are Complete guide that how can you get LESCO New Connection.

Documents Required for LESCO New Connection

LESCO New Connection

Prepare all Documents:

Assemble the following documents:

  1. Your property document copy (e.g., Property File or Registry)
  2. Attested the applicant’s CNIC copy
  3. A certified copy of the eyewitness’s CNIC
  4. Copy of the Neighbor’s LESCO bill 
  5. Test Report that are provided by Electrical Contractor
  6. Applicant Undertaking
  • File Size confirmation: Make sure that each file contains a size of 300kb as to meet submission requirements.
  • Visit the LESCO Web Portal: visit the LESCO web online portal for applying new connection. Submit all required documents on it and apply for new connection easily.
  • Terms and Conditions: Click/check-in all the terms and conditions for proceeding the application. Click on submit.
  • Wait for Confirmation: After submission all details, LESCO will verify and process your connection application accordingly.

What is LESCO Demand Notice (DN)?

A demand notice (DN) is a challan form issued by LESCO (WAPDA) for new electricity connection requests. It specifies the fee that the applicant must pay at the nominated bank that mentioned on the notice to proceed for new connection.

Demand Notice Fee Charges

Lesco demand notice fee is round about Rs.7240 to Rs.10500 for a single-phase Meter. This is an estimate idea fee but we prefer to contact the nearest concerned office and confirmed from them.And if, you want three phase connection. So, three-phase connection price is around Rs.33,500 to Rs.235,000 rupees.

Lesco new connection charges

Before applying for new connection, you must know about all the charges that applied in processing of new connection, here is some discuss below:

  1. New Connection Charges
  2. Security Deposit 
  3. Demand Notice Fee 
  4. Charges of Meter Installation
  5. Service Connection Charges.

Download LESCO Application Form for new connection. 

Download or print the application form from the following link:

Print Application Form

Sub divisional Information for LESCO New Connection 

Complete subdivision information for new connection in the following:

  • Distribution Type: Choose “LESCO” from the below menu under the circulation corporations. If, you are looking for a new connection to apply it is for you. This is a straight and simple process and should be done easily.
  • Select Category Type: This is depends upon your required load (in kW), choose your suitable category. You can also choose your desired load from menu.
  • Choose Subdivision: In last step, identify your subdivision and select it from the provided menu. Make sure that you must choose correct subdivision, to avoid any kind of issues during the process.

LESCO New Connection Application Tracking or Name Change Status check

  1. Visit the Website:
    • Go and visit the www.enc.com.pk.
  2. Select the Type:
    • Choose application type either “New Connection” or “Change of Name” from available options menu.
  3. Pick Your Electricity Provider:
    • Select your electricity provider company (e.g., LESCO, FESCO, KESCO, or IESCO) from the menu.
  4. Enter your Tracking ID:
    • Enter the “Tracking ID” that the ENC provided you with when you filed your application.
  5. check the Status:
    • To check your application status, click the “submit” button and check the status. That’s it.

If you follow these simple steps, you can easily track your LESCO new connection or name change status.

Installation of Meter

When your application for connection will approve then your new meter will be installed at your chosen location. It is mandatory to pay your demand notice before meter installation.

Time Required for New Connection Category-Wise

Category-wiseTime Required
Current level up to 400V and Load Up to 15 kW1 month
Current level up to 400 Volt and load up to 70 kW1 month and 23 days
Current level up to 400 Volt and load up to 500 kW2 month and 13 days
Current level 11 or 33 Kilo Volt and Load up to 5000 kW4 month and 16 days
Current level up to 66 Kilo Volt and aboveMore than 1 year

The three main category we discuss here:

Time Frame Required for Category-1 (load 1kW-15kW)

Time Frame Required for Category-1(load 1kW-15kW)
 

ProcessTime Required
After the successful proposal of the application, the office will produce a acceptance and assign a seniority number to the application on the register.1 Day
The inspection team will visit the place and inspect whether they can be provided easily or not. They will also inform to candidate as well.3 Days
If a connection can be provided, the prices will be valued.2 Days
The office will deliver a DN to the applicant either in person or via mail.2 Days
The client will provide the paid demand notice voucher in the office.2 Days
The applicant will submit the test report in the office and the office will verify it.3 Days
The concerned office will prepare a priority list report according to the demand notice paid date.1 Day
Service connection orders will be issued by the concerned office.3 Days
The office will provide the required equipment for set up a connection.3 Days
The store will deliver the essential equipment.5 Days
When the required equipment is received, the concerned office will hire persons to install the connection.5 Days
Total time required30 Days

Time Frame Required for Category-2 (Load 16kW-70kW/ 400 volts)

ProcessTime Required
After the successful submission, the office will produce a receipt form and assign a seniority number to the application on the register.1 Day
The inspection team will visit the place and inspect whether they can be provided easily or not. They will also inform to applicant accordingly.4 Days
If a connection can be provided, the costs will be estimated.3 Days
The office will deliver a demand notice to the applicant either in person or via mail.4 Days
The applicant will submit the paid demand notice receipt in the office.2 Days
The applicant will submit the wiring test report in the office and the office will verify it.5 Days
The concerned office will prepare a priority list report according to the demand notice paid date.2 Day
Service connection orders will be issued by the concerned office.4 Days
The office will make a call to store to provide the compulsory tools to set up a connection.15 Days
The store will afford the required equipment.7 DAYS
When the required equipment is received, the concerned office will hire persons to install the connection.6 Days
Total time required53 Days

Time Frame Required for Category-3 (Load 71kW-500kW/ 400 volts)

ProcessTime Required
After the successful form submission, the office will show a receipt and assign a seniority number to the application on the register.1 Day
The inspection team will visit the place and inspect whether they can be provided easily or not.4 Days
If a connection can be provided, the costs will be estimated.2 Days
The concerned office will accept the installation of the connection.4 Days
The applicant will submit the paid demand notice receipt in the office.4 Days
The applicant will submit the written test report in the office and the office will verify it.4 Days
Service connection orders will be issued by the concerned office.2 Days
The office will make a call to store to provide the compulsory tools to set up a connection.15 Days
After receiving the stationary, the committee consisting of DMO,
AMO and MT office will hire the persons to install the connection.
37 Days
Total time required73 Days

LESCO New Connection for Industries and Corporate Companies

In order to set up an industrial connection, you just want to provide the following documents:

  • Copy of the Affidavit Form
  • signatory’s favor of Board of Directors resolution.
  • Verified copy of the association’s memorandum of articles
  • Verified Accurate Copy of Form-29

Meter Replacement

Causes for Meter Replacement

The old meter will be replaced if it has reading fault, out-of-date or consumer facing any other issue. when consumer file a complaint, the meter has been replaced.

Required Documents Submission

In the replacement application, all you need to submit is, a photocopy of the National Identity Card (CNIC) or related ownership documents.

Estimated Time for Replacement

The estimate time for meter replacement, is within 7-10 days’ time period after file the complaint.

What is LESCO MIS?

The determination of Lesco’s Management Information Systems (MIS) is to influence technology for enhancing human security and productivity. MIS ensures that professionals may accomplish more and more in this day and age by engaging with computerized processes, whether it is through better decision-making, resource efficiency, expand their experience or operational management. It plays a vital role in supporting business operations by gathering and analyzing data in an organization

Making Better Business with Lesco MIS

  • MIS supports the business in their activities by collecting and analyzing data across their all-supervision planes.
  • It helps businesses to track best-selling items for better business.
  • Many businesses participate with MIS, for gain a competitive advantage in market.
  • MIS professionals develop for implementation corporate systems to improve business operations easily.
  • They develop a link between company and their clients to establish modern information-sharing systems.

Conclusion

In this article we have discussed how we can get LESCO new connection? Also learned about prices and complete figures about LESCO new connection information. So, Stay and visit Us for latest updates about LESCO. If you want to Check your LESCO Bill Online Must Visit here where you can download and print your LESCO Bill Online.